Day 150, 27 March 2013


Working out the logistics, as Big Blue approaches the narrow end of the work site. 

On 13 March, i posted pictures of a humungous circular saw cutting into the retaining wall. At the time, i interpreted this as a sign that the wall was about to come down, but it was actually part of the process of trimming and strengthening that section of the wall in preparation for the present stage of the work (the section of the wall that was worked on is visibly whiter in this picture). 






2 comments:

  1. Replies
    1. It's a lot of fun to watch (even though it has driven me to wear earplugs). It has so many different moving parts that it seems to be going in ten directions at once.

      Delete

This blog exists for one purpose: to follow the progress of the CTA substation project. Your comments relevant to that topic are very welcome.