It's been a busy few days, and a lot of the remaining tasks have been finished. The first three pictures show the status of the back wall last Saturday, with one section still needing the brickwork. Note the superstructure on the roof supporting the scaffolding.
On Monday, there was a lot of activity on the roof.
By late this afternoon, work was completed on several fronts. I hope the lighting in the pictures
isn't too distracting; it was late afternoon and the sun was shining brightly
when i got the chance to take these pictures.
Decorative iron gate installed at the south end of the substation. |
The plywood forms have been removed, revealing the new section of the retaining wall |
The view from the Pratt Blvd. end of the worksite. |
The brickwork on the trackside as been completed |
Anther view of the back wall |
A sure sign that the work is finished on the trackside wall: the scaffolding and related superstructure has been removed. |