Friday, May 24, 2013

Day 208, 24 May 2013

What appears to be a cement mixture is being pumped into the area of the tiebacks. 




A new notice was posted around the neighborhood today regarding the next stage of construction: the building of the substation; installation of sewer, water, and electrical service for the building; and installation of the electrical equipment that it is the reason the substation is being built. It gives the range of dates for the actual building of the substation as starting on 12 June and continuing until 28 February of next year. So it looks like this stage of the project is nearing completion. 