Monday, September 16, 2013

Day 323: 16 September 2013

This morning, the carpenters began dismantling the gang forms.

This involved some serious wall-climbing.

This evening, the gang forms were gone,
revealing part of the concrete wall that was poured on Saturday.

Meanwhile at the north end, another large pile of rebar is waiting to be installed.