Friday, September 27, 2013

Day 334: 27 September 2013

The semicircular metal supports and wooden forms for the two arches were installed today in preparation for the next round of concrete, which is scheduled for tomorrow.  As the shadows indicate, the first three pictures were taken in the morning, the last two at the end of the day.






No comments:

Post a Comment

This blog exists for one purpose: to follow the progress of the CTA substation project. Your comments relevant to that topic are very welcome.