Thursday, October 24, 2013

Day 361: 24 October 2013

Work continues on the west wall. I haven't had confirmation on whether this represents the actual full height of the building (which would be different from what i had been told earlier) or if it might be a wall separating the substation from the tracks rather than actually being part of the substation itself. I know that the original plans showed the height of the building as being about 35 feet from street level, and this new structure is considerably higher than that. Stay tuned....

Threading another length of rebar through the west wall.

Climbing the walls

The view at the end of the day:



1 comment:

  1. Getting pretty high. Will ruin your views, but muffle the "L" noise.

    ReplyDelete